Re: review of DRAFT_Lithium_Release_Plan_ckd
Ed Warnicke (eaw) <eaw@...>
Colin,
toggle quoted messageShow quoted text
Per the discussion about leaving adequate time M0->M1 and M1->M2, I wanted to throw out some concrete date proposals. I think you’ve expressed agreement that M0 should start from roughly when we approve the SR Plan (which we are hoping to do this Thursday). For sake of discussion, I wanted to make a concrete date proposal (all dates for which offsets apply are offset 0 dates, with the 2 week and 4 week add for offset 1 and offset 2 respectively: M0 :11/7/2014 Last Date for new Projects: Nov 27 (offset0) M1 12/12/2014 ( 1 extra week for Thanksgiving ) M2: 1/23/2015 ( 2 extra weeks for Christmas) M3: 2/20/2015 M4: 3/20/2015 M5: 4/17/2015 RC0: 5/29/2015 RC1: 6/12/2015 RC2: 6/26/2015 Formal Release: 7/3/2015 SR1: 8/14/2015 SR2: 9/25/2015 Thoughts? Ed
On Nov 3, 2014, at 12:47 PM, Kent Watsen <kwatsen@...> wrote:Leadership & CommunicationI'm curious what the logic is here? Is it to make it italics or bold?
|
|