Re: Saving infra resources


Abhijit Kumbhare
 

About the stuff below - to address Robert's point about quiescent period and xtend breaking us - maybe reduce the frequency from daily to weekly (or some other suitable interval like twice a week)?

On Fri, Jan 18, 2019 at 2:11 AM Robert Varga <nite@...> wrote:
On 18/01/2019 05:09, Anil Belur wrote:

> I'd think this should be fixed in AR/parent job that is triggering these
> int/dist jobs every day. The question that needs to be answered is if we
> do need to build AR (and int/dist jobs) every day even if there are no
> new changes to the project participating in the AR repos.

Since we do not have fully-reproducible builds we cannot assume the
build does not need to trigger just because the source code has not
changed -- one example would be a quiescent period and xtend breaking us :)

Regards,
Robert