Lithium Project Proposal Deadline


Pugh, Rex <rex.pugh@...>
 

Would anyone oppose moving the Lithium Project proposal deadline out 1 week. From Oct 23rd to Oct 30?

 

That would mean either:

a.       Reducing the comment period to 1 week and keeping the 11/6 M1 deadline, or

b.      Extending the M1 also extending the M1 deadline by a week.

 

How many other project proposals are queued up to the TSC for the next 3 meetings?

 

We would like to propose:

·         Device Driver Framework

·         2-node HA (in conjunction with Dell)

·         API additions

 

We will do our best to meet the deadline, but we are also trying to coordinate with other related projects and will be pressed to get closure before next Thursday.

 

Is there flexibility to bring a project in after the deadline as long as we prove a sufficient plan to meet the final release milestones.

 

Thanks

 

Rex Pugh

 

 


Colin Dixon
 

Hi Rex,

Ultimately, this will have to be decided by the TSC, so I'm cc'ing the TSC list.

--Colin


On Thu, Oct 16, 2014 at 3:24 PM, Pugh, Rex <rex.pugh@...> wrote:

Would anyone oppose moving the Lithium Project proposal deadline out 1 week. From Oct 23rd to Oct 30?

 

That would mean either:

a.       Reducing the comment period to 1 week and keeping the 11/6 M1 deadline, or

b.      Extending the M1 also extending the M1 deadline by a week.

 

How many other project proposals are queued up to the TSC for the next 3 meetings?

 

We would like to propose:

·         Device Driver Framework

·         2-node HA (in conjunction with Dell)

·         API additions

 

We will do our best to meet the deadline, but we are also trying to coordinate with other related projects and will be pressed to get closure before next Thursday.

 

Is there flexibility to bring a project in after the deadline as long as we prove a sufficient plan to meet the final release milestones.

 

Thanks

 

Rex Pugh

 

 


_______________________________________________
project-proposals mailing list
project-proposals@...
https://lists.opendaylight.org/mailman/listinfo/project-proposals



Mohnish Anumala
 

I would request the same. We are working with HP and Cisco folks to create a 2-node cluster/HA proposal.

Work is in progress and certainly we can use more time.

 

Thanks,

--Mohnish

 

From: project-proposals-bounces@... [mailto:project-proposals-bounces@...] On Behalf Of Pugh, Rex
Sent: Thursday, October 16, 2014 1:25 PM
To: project-proposals@...; discuss@...; release@...
Subject: [Project-proposals] Lithium Project Proposal Deadline

 

Would anyone oppose moving the Lithium Project proposal deadline out 1 week. From Oct 23rd to Oct 30?

 

That would mean either:

a.       Reducing the comment period to 1 week and keeping the 11/6 M1 deadline, or

b.      Extending the M1 also extending the M1 deadline by a week.

 

How many other project proposals are queued up to the TSC for the next 3 meetings?

 

We would like to propose:

·         Device Driver Framework

·         2-node HA (in conjunction with Dell)

·         API additions

 

We will do our best to meet the deadline, but we are also trying to coordinate with other related projects and will be pressed to get closure before next Thursday.

 

Is there flexibility to bring a project in after the deadline as long as we prove a sufficient plan to meet the final release milestones.

 

Thanks

 

Rex Pugh