Controller M3 Status


Ed Warnicke (eaw) <eaw@...>
 

Controller
OpenDaylight Helium M3 Status update.


M2 Deliverable Status:

Final Release Plan Complete:  YES

Gerrit/Jenkins merge process successfully pushes project binary artifacts to Nexus repo: YES

M3 Deliverable Status:

Continuous Integration Test Working: YES
Continuous Integration Testing is where your project has a Jenkins job which will rebuld and retest to an appropriate level when a project you depend on publishes new artifacts to the nexus repo.

Project Documentation has started:  - It is not clear what this means, as it doesn’t appear to have any clear definition.

Project Development Status Summary: 

MD-SAL: Lazy deserialization from Binding-Independent Format:    DONE
MD-SAL: Datastore Tracer: DROPPED
MD-SAL: Clustering: Design Documentation Review: DONE
Reviewed with: Group Based Policy Team,  Jan Medved,  Robert Varga,  Tony Tkacik,  Colin Dixon, Prasanna Huddar, Srikar Rajamani, Chandramouli Venkataraman, Sasidharan Sambhasivan
MD-SAL: Clustering: Initial Sharding Manager: DONE
MD-SAL: Clustering: Distributing Shards in a cluster: Delayed - To be completed by 7/09/2014
MD-SAL: Clustering: Initial Remote Data Change Notification Manager: DONE
MD-SAL: Clustering: Initial Remote Routed RPCs: Delayed - To be completed by 7/09/2014
MD-SAL: Clustering: Initial Notifications: Delayed - To be completed by 7/18/2014

From M2: Switch over to default use of openflowplugin: DONE

Overall: Yellow trending to Green.

Ed