M4 status of ALTO


Y. Richard Yang
 

Hi all,

This is an update of our M4 status:

1)  API freeze achieved. (All externally accessible APIs [Stable and Provisional] may not be modified.)  
Yes

2)  Document word counts for each documents: (Please provide word counts for ascii docs) 
docs/manuals/user-guide/src/main/asciidoc/alto/odl-alto-user.adoc: 348 words
docs/manuals/dev-guide/src/main/asciidoc/alto/odl-alto-dev.adoc: 202 words
docs/manuals/install-guide/src/main/asciidoc/alto/odl-alto-install.adoc: 235 words 

3)  Project meet the requirements to be included in Maven Central [0] 
Yes (Javadoc/sources, GPG key, Sufficient Meta)

4)  Defined a simple system test for karaf distribution with recommended features installed. 
Still working on tests: feature template, system test. Expect to be done within 5 days.

Thanks.
Y